Verizon Wireless Data Center

The restricted site and limited access for the Verizon Wireless Data Center were no match for Sure Steel, Inc. and their proficient project team. The 2-story, 130,500 square foot Data Center in Rocklin, CA required heavy coordination and strategic planning from Sure Steel, Inc. in order to supply and erect the 1,405 tons of steel safely and on time, but Sure Steel, Inc. worked closely with all project stakeholders to complete the $4.6M turnkey contract in a safe and efficient manner. Sure Steel, Inc. leveraged just-in-time deliveries to overcome the minimal laydown yard, utilized 19,500 man hours and overtime to meet the aggressive 12 week time frame, and provided a full-time on-site safety manager to make sure that everyone went home safe each day.