Sure Steel was contracted to supply and install architectural finishes for this new processing plant at KUC’s Moly Autoclave Processing facility in Magna, Utah. The project was very congested and Sure Steel was able to complete all of the cladding on 28 buildings, including 168,000 square feet of roofing and 320,000 square feet of siding, totaling 51,000 man hours without an incident.

KUC Moly Autoclave Processing Plant
  • Location: Magna, UT
  • Surface Area: 488,000 SqFt of panels
  • Contractor/Owner: Jacobs Engineering
  • Value: $5,000,000 - $10,000,000
  • Category:
  • Scope: Supply and Erect
  • Type: Metal Wall Panels

Safety Stats

HOURS WORKED

2M

Without Lost Time

EMR

0.52

Experience Modification Rate (7/1 to 6/30)

LTIR

0.00

Lost Time Incident Rate

DART

0.00

Days away, restricted, transferred (1/1 to 12/31)